PÖYRY TO DESIGN PROPAPIER'S NEW PM2 IN GERMANY


Pöyry has been awarded an engineering contract by Propapier GmbH for
its PM2 project at a new site in Eisenhüttenstadt, Germany. The
project is subject to final permit approval. The value of the
contract is about EUR 10 million.

The new paper machine will produce about 650 000 t/a of
testliner/fluting paper grades and is scheduled to start production
in 2009. The assignment covers procurement, engineering, erection
supervision, commissioning and start-up services for implementation
of the paper mill project. The latest technology will be applied in
the process solutions of PM2 targeting at high quality grades taking
into account stringent environmental aspects.

The long-standing previous cooperation with Propapier's project
management forms a good basis for implementing a successful project.
This assignment is also a continuation to several recent
implementation projects, such as Saica PM10 and Schwarza PM1,
performed by Pöyry in the packaging paper area.

Pöyry is a global consulting and engineering firm focusing on the
energy, forest industry and infrastructure & environment sectors.
Pöyry's net sales in 2007 amounted to about EUR 720 million and it
employs 7300 experts.

PÖYRY PLC

Erkki Pehu-Lehtonen
President and CEO

Teuvo Salminen
Deputy to President and CEO

Additional information by:
John Lindahl, President of Forest Industry Business Group, Vantaa,
Finland
Tel. +358 10 33 22951
Nicholas Oksanen, Vice President, Pöyry Forest Industry Oy, Vantaa,
Finland
Tel. +358 10 33 22294

www.poyry.com

DISTRIBUTION:
OMX Nordic Exchange Helsinki
Major media